NGCP SCHEDULED POWER INTERRUPTION

WHEN: July 29, 2020 (Wednesday)
7:00 am to 6:00 pm

WHERE: ALCALA SUBSTATION
FEEDER 31
Portion of Piat - Catarauan
Part of Amulung West
Bayabat, Bacring, Nagsabaran, La Suerte, Nanuccauan, Masical, Catarauan
Part of Alcala
Pared, Baculud, Masin, Agani, Centro Sur, Centro Norte, Tupang, Maraburab, Piggatan, Carallangan, Tamban, Malalatan, Afusing Daga, Afusing Bato, Cabuluan, Abbeg, Dalaoig, Pussian, San Esteban, Portion of Baybayog

FEEDER 32
Whole Area of Baggao
Bayan - Lapi, Penablanca
Part of Alcala
Calantac, Pinopoc, Part of Baybayog

FEEDER 33
Whole Area of Iguig except Sta. Teresa & Bayo
Whole Area of Amulung East
Portion of Alcala (Portion of Baybayog, Jurisdiccion, Pagbangkeruan, Damurug)

WHY: To facilitate replacement of rotten wood pole along the Tuguegarao-Camalaniugan-Sta. Ana 69kV Line.